Using statistical control charts to monitor duration-based performance of project

Nooshin Yousefi, Ahmad Sobhani, Leila Moslemi Naeni, Kenneth R. Currie

Abstract


Monitoring of project performance is a crucial task of project managers that significantly affect the project success or failure. Earned Value Management (EVM) is a well-known tool to evaluate project performance and effective technique for identifying delays and proposing appropriate corrective actions. The original EVM analysis is a monetary-based method and it can be misleading in the evaluation of the project schedule performance and estimation of the project duration. Earned Duration Management (EDM) is a more recent method which introduces metrics for the project schedule performance evaluation and improves EVM analysis. In this paper, we apply statistical control charts on EDM indices to better investigate the variations of project schedule performance. Control charts are decision support tools to detect the out of control performance. Usually, project performance measurements are auto-correlated and not following the normal distribution. Hence, in this paper, a two-step adjustment framework is proposed to make the control charts applicable to non-normal and auto-correlated measurements. The case study project illustrates how the new method can be implemented in practice. The numerical results conclude that that employing control chart method along with analyzing the actual values of EDM indices increase the capability of project management teams to detect cost and schedule problems on time.


Keywords


Earned Duration Management, Statistical Control Charts, Project Performance Evaluation

References


Abba, W., & Niel, F.A., (2010). Integrating technical performance measurement with earned value. Measurable News, 4, 6-8.

Aliverdi, R., Naeni, L.M. & Salehipour, A., (2013). Monitoring duration and cost in a construction by applying statistical quality control charts. International Journal of Project Management, 31(3), 411- 423.

Azman, M. A., Abdul-Samad, Z. & Ismail, S., (2013). The accuracy of preliminary cost estimates in Public Works Department (PWD) of Peninsular Malaysia. International Journal of Project Management, 31(7), 994-1005.

Barraza, G. A., & Bueno, R.A., (2007). Probabilistic control of performance using control limit curves. Journal of Construction Engineering and -ASCE. 133 (12), 957–965.

Batselier, J., & Vanhoucke, M., 2015a. Evaluation of deterministic state-of-the-art forecasting approaches for duration based on earned value. International Journal of Project Management, 33(7), 1588-1596.

Bisgaard, S., & Kulahci, M. (2011). Time series analysis and forecasting by example. Wiley.

Book, S. A. (2006). Earned schedule and its possible unreliability as an indicator. The Measurable News, 7-12.

Chatfield, C., (2016). The analysis of time series: An introduction. CRS press.

Chen, H. L., Chen, W. T., & Lin, Y .L., (2016). Earned value: Improving the predictive power of planned value. International Journal of Project Management. 34(1), 22-29.

Colin, J., & Vanhoucke, M. 2014. Setting tolerance limits for statistical control using earned value. Omega. The International Journal of Science, 49, 107–122.

Colin, J., Martens, A., Vanhoucke, M., & Wauters, M., 2015. A multivariate approach for top-down control using earned value. Decision Support Systems, 79, 65-76.

D’Agostino, R.B., & Stephens, M.A., (1986). Goodness of Fit Techniques. Marcel Dekker Inc.

Fleming, W., & Koppelman, J.M., (1996). Earned Value. 2nd edition, Upper Darby, PA: Institute.

Franco, B.C., Celano, G., Castagliola, P. & Costa, A.F.B., (2014). Economic design of Shewhart control charts for monitoring auto-correlated data with skip sampling strategies. International Journal of Production Economics, 151, 121-130.

Henderson, K. (2003). Earned schedule: A breakthrough extension to earned value theory? A retrospective analysis of real data. The Measurable News, 6.

Khamooshi, H., & Golafshani, H., (2014). EDM: Earned Duration, a new approach to schedule performance and measurement. International Journal of Project Management, 32, 1019–1041.

Leu, S.S., & Lin, Y.C., (2008). performance evaluation based on statistical control techniques. Journal of Construction Engineering and -ASCE 134 (10), 813–819.

Lipke, W., (2003). “Schedule is different. The Measurable News Summer, 31–34.

Lipke, W., & Vaughn, J., (2000). Statistical control meets earned value. The Journal of Defense Software Engineering 16-20.

Lipke, W., Zwikael, O., Henderson, K., & Anbari, F., (2009).

Prediction of outcome: the application of statistical methods to earned value and earned schedule performance indexes. International Journal of Project Management, 27, 400–407.

Meredith, J.R., Mantel, S.J., & Shafer, S. (2015). : A Managerial Approach 9th edition. John Wiley & Sons Inc.

Montgomery, D. C. (2009). Introduction to statistical quality control, 6th Ed. John Wiley & Sons Inc.

Narbaev, T., & Marco, A.D., (2014). An earned schedule-based regression model to improve cost estimate at completion.

International Journal of Project Management. 32 (6), 1007–1018.

Oakland, J.S., (2007). Statistical control. Routledge.

Institute, (2004). A guide to body of knowledge, 3rd edition. Institute, Newtown Square, PA.

Institute, (2005). Practice standard for Earned Value, 2nd edition. Institute, Newtown Square, PA.

Institute, (2008). A guide to body of knowledge, 4th edition. Institute, Newtown Square, PA.

Institute, (2013). A guide to the body of knowledge. Institute, Newtown Square, PA.

Rodríguez, J.C.M, Pascual, J.L., Molina, P.C., Marquez, F.P.C., (2017). In An overview of earned value in airspace industry. Proceedings of the Tenth International Conference on Science and Engineering, 2017, Springer, 1465-1477.

Russo, S. L., Camargo,M. E., & Fabris, J. P. (2012). Practical concepts of quality control. In-Tech, Rijeka, Croatia.

Salari, Mostafa, Nooshin Yousefi, and Mohhmad Mahdi Asgary. "Cost Performance Estimation in Construction Projects Using Fuzzy Time Series." Project Management: Concepts, Methodologies, Tools, and Applications. IGI Global, 2016. 359-370.

Salehipour, A., Naeni, L.M., Khanbabaei, R. & Javaheri, A., (2015). Lessons Learned from Applying the Individuals Control Charts to Monitoring Autocorrelated Performance Data. Journal of Construction Engineering and, 142(5), 15-27.

Sobhani, A. and Wahab, MIM (2018) "The effect of working environment-ill health aspects on the carbon emission level of a manufacturing system", Computers & Industrial Engineering,113,75-90.

Thor, J., Lundberg, J., Ask, J., Olsson, J., Carli, C., Härenstam, K.P. & Brommels, M., (2007). Application of statistical control in healthcare improvement: systematic review. Quality and Safety in Health Care, 16(5), 387-399.

Turner, J.R., (2010). Evolution of as evidenced by papers published in the International Journal of Project Management, 28(1), 1-6.

Vandevoorde, S., & Vanhoucke, M., (2006). A comparison of different duration forecasting methods using earned value metrics. International Journal of Project Management, 24 (4), 289-302.

Wei, W.S., (1994). Time series analysis. Addison-Wesley publication.

Xie, M., Goh, T.N., & Kuralmani, N. (2002). Statistical models and control charts for high quality es. Springer publication. 207-235.

Yousefi, N. (2018). "Considering financial issues to estimate the project final cost in earned duration management" Iberoamerican Journal of Project Management, 9.2, 01-13.


Full Text: PDF

Refbacks

  • There are currently no refbacks.




______________________________________________________________________________

The Journal of Modern PM (ISSN: 2317-3963) | info@journalmodernpm.com